The tentative dates for completion of North Main Street, Grove Street, and Laurel Hill Avenue is by mid-to-late June, and completion of Church Street, High Street, Sayles Avenue and Irving Avenue by the end of August.


 

May 30, 2017

Pascoag Utility District (PUD) would like to update our water customers on the progress of the Phase 2 Water Main Cleaning/Lining Project.

North Main Street, Grove Street and Laurel Hill Avenue’s water mains have been lined. The newly lined water mains are in the process of being chlorinated and then will be tested for bacteria, prior to customers being removed from the temporary bypass mains and put back on the original main. Church Street has been moved to the bypass mains and the original main is out of service and being prepared for lining.

Biszko Contracting Corp. will begin work on Sayles Avenue and Irving Avenue during the week of June 5th.


 