Project Updates

The tentative dates for completion of North Main Street, Grove Street, and Laurel Hill Avenue is by mid-to-late June, and completion of Church Street, High Street, Sayles Avenue and Irving Avenue by the end of August.


 

May 30, 2017

Pascoag Utility District (PUD) would like to update our water customers on the progress of the Phase 2 Water Main Cleaning/Lining Project.

North Main Street, Grove Street and Laurel Hill Avenue’s water mains have been lined. The newly lined water mains are in the process of being chlorinated and then will be tested for bacteria, prior to customers being removed from the temporary bypass mains and put back on the original main. Church Street has been moved to the bypass mains and the original main is out of service and being prepared for lining.

Biszko Contracting Corp. will begin work on Sayles Avenue and Irving Avenue during the week of June 5th.


June 7, 2017

Broad Street and High Street will be taken out of service to change two valves as part of the cleaning/lining project.


June 13, 2017

Pine Street will be taken out of service to replace a valve on the corner of Pine and Howard.


June 15, 2017

Old Wallum Lake Road, East Wallum Lake Road, Laurel Ridge and Marion Avenue will be taken out of service today to change the valve cluster at the top of Church Street near Serio’s.


June 16, 2017

Old Wallum Lake Road, East Wallum Lake Road, Laurel Ridge and Marion Avenue will be taken out of service today to change the valve cluster at the top of Church Street near Serio’s. The repair had to continue into a second day to finish.


June 27, 2017

Biszko begins the cleaning and lining of the water mains on Sayles and Irving Avenue. Church Street will start to be converted back over to the original water main.


July 11-12, 2017

Major valve replacement project on High Street.


July 18, 2017

Bypass pipes were laid out on Pine Street today and were charged and chlorinated. Sayles and Irving Ave’s lines were also charged and chlorinated.


July 26, 2017

Customers on Sayles and Irving Ave are being removed from the bypass line and back to the original main.


July 31, 2017

Half-Caps were replaced today at two locations-Pine Street and Sayles Ave. Pascoag Main Street had a water outage for 2 hours to keep pressure off of the Sayles Ave work.


 